By Jo Martin · Published November 4, 2026

153+
Cities Served
50
States Covered
24–72h
Scheduling
100%
NCCCO Certified
✓ NCCCO Inspector Certified ✓ OSHA & ASME B30 Compliant ✓ Photo-Documented Reports ✓ Independent Third-Party ✓ EM 385-1-1 · USACE · NAVFAC

By Jo MartinNov 4, 202634 min read

Three plant engineers in hard hats reviewing a tablet in front of refinery process columns

Short answer: Plan a turnaround crane inspection like a trade: give it a work order, a slot and a crew in the schedule of record, and put it in the first days of the window. Under 1910.179(l)(3)(i), unsafe conditions found by inspection are corrected before the crane resumes operation, so early inspection is what leaves time to repair before restart.

Turnaround season is the great contradiction of crane inspection scheduling. A turnaround crane inspection is the only chance some equipment gets to be examined properly at all — process cranes over live lines, hoists inside energized cells, runway steel nobody can reach while production runs, anything that cannot stop while the plant runs. The turnaround is also the exact window when every contractor in three counties is inside your fence competing for the same lifts, the same aerial platforms, the same lockout points and the same maintenance planners.

Inspections that are not sequenced into the plan get squeezed out of it, and the crane goes another year on borrowed paperwork.

This guide covers the planning side of that problem: deciding which cranes, hoists and below-the-hook gear get inspected inside the window, building the scope and the equipment register long before the gates open, putting the inspection ahead of the trades that fix things so findings can still be repaired before restart, lining up lockout, access, parts and load-test logistics, and running the deficiency triage and return-to-service sequence that decide whether each crane restarts with the plant.

It is written for turnarounds, shutdowns and outages at plants where overhead and gantry cranes fall under 29 CFR 1910.179, with notes on the slings and mobile cranes that come through the gate for the outage.

Why is the outage the inspection window?

A running plant limits how deeply anyone can look at a crane. The inspector can watch it run, listen to it, check the hook and the rope that is visible, and work through the frequent inspection items from the floor.

What the inspector usually cannot do is open the gear cases, take the brake apart, walk the runway, run the full length of rope off the drum, or open the control panels with the energy isolated, because each of those takes the crane, and often the area under it, out of production. The outage removes those limits, which changes what the inspection should include.

The federal text explains why that matters. Under 1910.179(j)(3), the periodic inspection is a complete inspection of the crane that includes everything in the frequent inspection plus a list of items most of which are best reached with the crane parked and locked out:

Periodic itemParagraphWhy it waits for the outage
Deformed, cracked or corroded members1910.179(j)(3)(i)Girders, end trucks and runway steel over process equipment need a lift or a walkway and a crane that is not moving
Loose bolts or rivets1910.179(j)(3)(ii)End truck, girder and rail clip connections are checked by hand, up close
Cracked or worn sheaves and drums1910.179(j)(3)(iii)Grooves and flanges are seen properly with the block lowered and the rope slack
Worn, cracked or distorted pins, bearings, shafts, gears, rollers, locking and clamping devices1910.179(j)(3)(iv)Gear cases and couplings are opened, which means covers off and the drive isolated
Excessive wear on brake system parts, linings, pawls and ratchets1910.179(j)(3)(v)Linings and pads are measured with the brake opened up
Load, wind and other indicators over their full range1910.179(j)(3)(vi)A full-range check needs known loads at the hook
Pitting or deterioration of controller contactors, limit switches and pushbutton stations1910.179(j)(3)(x)Panels and pendant enclosures are opened with the energy isolated

Two more items belong on the outage list even though they are not periodic items. Paragraph (m)(1) calls for a thorough inspection of all running ropes at least once a month, and the outage is the time to examine the full length, including the wraps that never leave the drum in normal service. The terminations at both ends deserve the same attention, and wire rope end connections covers what to look for.

And paragraph (j)(2)(iii) sets the hook limits used throughout this guide: a hook with cracks, more than 15 percent in excess of normal throat opening, or more than 10 degrees of twist from the plane of the unbent hook goes to (l)(3)(iii)(a), which says it shall be discarded. A cleaned hook with the block on the floor is the easiest hook in the plant to measure, and the best one to send for crack testing.

The outage cannot replace the calendar, though. Under (j)(1)(ii)(b) the periodic interval is 1 to 12 months, set in (j)(3) by the crane’s activity, severity of service and environment. Some process units run a long time between turnarounds, and no periodic interval stretches to meet them. The periodic inspections keep running on the interval the crane needs, which the periodic crane inspection page lays out, and the outage adds the depth that a running plant cannot give. Use the stillness for what needs it.

A shutdown inspection that only repeats what a running-plant inspection could have done has wasted the rarest resource in the building: stillness.

What goes into a turnaround crane inspection scope?

Scope starts with a list of everything in the plant that lifts, not with a list of the cranes someone remembers. The equipment that gets missed in an outage is often the same equipment that gets missed all year: the monorail over a pump bay, the jib in the maintenance shop, the spreader beam hanging on the wall, the hoist that came with a skid package and never made it onto the inspection list.

Build the equipment register

The register is the planner’s tool, and it is worth more than any single inspection. One line per crane or hoist, with the fields the outage plan actually uses:

Register fieldWhat the outage plan uses it for
Unique ID, location and type (overhead, gantry, jib, monorail, hoist)Ties the work order, the lockout point and the inspection report to one machine
Rated load as marked under 1910.179(b)(5)Sizes any load test and confirms the marking is legible from the floor
Date of the last periodic inspection and the interval set for the craneShows whether the crane falls due before the next window would come
Open findings and monitor items from the last reportBecomes repair scope and the parts list
Energy isolation points and the lockout procedure that covers themLets the outage lockout plan include the crane instead of discovering it
Access method (lift, runway walkway, catwalk, scaffold) and who provides itPuts the inspector on equipment that is already booked
Manufacturer, model and the manual on fileSupplies the criteria for repairs, rope replacement and adjustments
Role in the outage: idle, standby, or working the turnaroundDecides when in the window the crane is inspected

Slings, rigging hardware and below-the-hook devices get their own register: tag or serial number, type, rated capacity for the hitches used, and the month of the last thorough inspection where one is required. That inventory is the difference between a rigging inspection that takes an afternoon and one that takes the first two days of the window.

Decide which cranes have to be inspected inside the window

Not every crane on the register needs outage time. Sorting them early frees outage hours for the cranes that do. The ones that belong inside the window:

Everything else can move out of the window. Frequent inspection items, function observations, sling inventories, document reviews and the inspections of cranes outside the outage boundary can be done in the weeks before, on a running plant, which keeps the outage hours for the work that needs stillness.

The cranes that work the turnaround

Turnarounds change how hard some cranes work. A maintenance bay crane that lifts a few times a week in production can run near its rated load several times a day during an outage, setting pumps, motors, valves and bundles. Those cranes need the deep inspection at the front of the window, before the heavy work, and the frequent inspection items in (j)(2) keep running daily while the outage lasts.

Paragraph (n)(3)(vii) adds an operator duty that matters more during an outage than at any other time: the brakes are tested each time a load approaching the rated load is handled, by raising the load a few inches and applying the brakes. If a heavy pick needs two cranes, (n)(3)(ix) requires one qualified responsible person in charge of the operation. Both are reasons to know the condition of those cranes before the first heavy pick, not to find out from the inspection report after the outage.

Slings, rigging hardware and below-the-hook devices

Outages multiply rigging. Every contractor brings slings and hardware, the plant pulls its own gear out of storage, and lifting beams that hang on a wall all year go to work. In general industry, 1910.184(d) requires each sling and all fastenings and attachments to be inspected for damage or defects each day before use by a competent person designated by the employer, and damaged or defective slings to be removed from service immediately. Paragraph (c)(14) says slings without affixed and legible identification markings are not used.

Alloy steel chain slings add a thorough periodic inspection under (e)(3), at intervals set by frequency of use, severity of service, the nature of the lifts and experience, and in no event at intervals greater than once every 12 months, with a record of the most recent month each sling was thoroughly inspected. Under (e)(4), new, repaired or reconditioned alloy chain slings are proof tested by the sling manufacturer or an equivalent entity before use, and the employer keeps the certificate.

Some host plants run a gate check on contractor rigging. That is a site practice, not a federal requirement. The federal text puts the daily inspection on a competent person designated by the employer whose people use the sling. A gate check is still worth planning, because a tagless sling found at the gate costs nothing and one found under a load costs the lift.

Spreader beams, lifting beams, coil lifters and other below-the-hook devices are inspected under ASME B30.20 and their own manufacturers’ instructions, and the case for treating them as equipment rather than tools is in below-the-hook device inspections. If the plant’s own gear needs a thorough inspection before the outage, it can be scheduled weeks ahead as a rigging inspection, outside the window entirely.

Mobile cranes that come through the gate

Big outages bring in crawlers and rough-terrain cranes for the lifts the plant cranes cannot make. Those machines arrive with their own inspection file, and the time to read it is at mobilization, not at the first pick. Which rule applies depends on the work.

Where the outage task counts as construction, 29 CFR 1926 Subpart CC applies, and 1926.1412 requires a post-assembly inspection by a qualified person under (c)(1) for a crane assembled on site, a shift inspection under (d), a monthly inspection documented and kept for at least three months under (e)(3), and an annual inspection by a qualified person documented and kept for at least 12 months under (f)(7).

In general industry, 1910.180 covers crawler, locomotive and truck cranes, and (d)(6) calls for monthly certification records on critical items such as brakes, crane hooks and ropes. How the two frameworks divide is covered in 1910.179 versus 1926.1412, and who owns the inspections on a rented unit is in rental crane inspection responsibility.

Start the plan at the last close-out

The best outage inspection plans start the day the previous outage ends, because that is when everyone knows what slipped. The milestones below are the planning moves that keep crane inspection inside the turnaround instead of next to it. The timing of each one follows your plant’s outage planning calendar, not a fixed number of weeks.

MilestoneCrane inspection planning task
Close-out of the last outageCarry every monitor item, deferred repair and access problem into the next outage scope while people still remember them
Through the yearPeriodic inspections continue on each crane’s interval, and each report adds findings to the outage list and shows which ones are trending
When the outage scope is being builtFreeze the equipment register, write the inspection scope crane by crane, and enter the inspection in the schedule of record with work order numbers, durations and crew needs
Before long-lead parts are orderedReview the likely findings against the last reports and confirm parts are ordered or on the shelf
When contractors are onboardedExchange lockout procedures, book shared access equipment, and book test weights and test rigging if a load test is likely
The pre-outage walkdownRun the frequent inspection items and function checks on the running plant, and confirm isolation points, access routes and the staging area for weights
Inside the window, first daysDe-energized inspection of the cranes that need repair time, with findings handed to the repair crews as they are found
Inside the window, last daysRe-inspection of repaired items, function tests, load tests where triggered, release from lockout
Restart and close-outRecords filed, and open monitor items become the first page of the next outage scope

Book the inspection like a contractor, not an errand

The inspections that survive a turnaround are the ones with a slot in the schedule of record — a work order number, a duration, a crew requirement and a named window. The ones that get dropped were “we’ll fit it in.” Treat the inspector as a trade: they need access, power state and support equipment defined in advance, and they can tell you exactly what those are if asked during planning instead of at the gate.

What an inspector usually needs defined before the window opens:

Sequence inspections ahead of the trades that fix things

The single most useful planning decision is where the inspection sits in the window. An inspection on the last day of an outage produces one of two things: a list for next year, or a crane that cannot restart. An inspection on the first days produces a repair list while the repair crews, the parts and the lockouts are all still in place.

Inspect early, repair inside the window

Under 1910.179(l)(3)(i), any unsafe condition disclosed by the inspections in (j) is corrected before operation of the crane is resumed, and adjustments and repairs are done only by designated personnel. In a turnaround, that sentence decides the schedule. A finding that is a safety hazard has to be fixed before the crane restarts, so the time between finding it and the planned restart is the only time there is to fix it. Inspecting early buys that time. Inspecting late spends it.

Run the dependency chain

A workable sequence for a crane that is both inspected and repaired in the outage:

  1. Pre-outage running inspection. Frequent inspection items, function checks and observation during operation, before the plant comes down, so obvious findings are known and parts are moving before the window opens.
  2. De-energized inspection under lockout. Structure, runway, rope over its full length, brakes, gear cases and electrical apparatus, on the first days the crane is available.
  3. Findings handed over as they are found. A verbal close-out before the inspector leaves each crane, then the written report, so repair crews are not waiting on paperwork.
  4. Repairs by designated personnel, to the manufacturer’s criteria, under (l)(3)(i).
  5. Re-inspection of the repaired items and a function test with power back on.
  6. Load test where a repair or alteration triggers one, late in the window, after the repair crews are finished.
  7. Release from lockout and return to service in the order described below.

Share access, and coordinate with paint, blast and scaffold crews

The lift that positions painters at the runway can position the inspector the same day, if someone thinks of it in planning. The order matters too. Inspection, and any crack testing of welds by non-destructive testing, goes before blasting and new coating on the same steel, because a fresh coat of paint over a crack hides it until the next time someone strips it.

Scaffolds built for other trades can give the inspector access to girders and runway steel, but they also become obstructions the moment the crane is asked to travel. Paragraph (b)(6)(i) requires a minimum clearance of 3 inches overhead and 2 inches laterally between the crane and obstructions, and (l)(2)(ii) says the crane is not operated after repairs until guards are reinstalled, safety devices reactivated and maintenance equipment removed. Temporary scaffolds, piping and staging in the crane’s path belong on the restart checklist for that reason.

Other cranes on the same runway

Turnarounds sometimes take one crane down while a second crane on the same runway keeps working for the outage. Paragraph (l)(2)(i)(e) requires rail stops or other suitable means to keep the working crane away from the idle one. That needs to be in the plan, with the means identified and installed, because an inspector or mechanic on the idle crane is exactly who the requirement protects.

Lockout, access and the function test

An inspection with covers off is servicing and maintenance in the sense of 1910.147, whose definition of servicing and/or maintenance names inspecting. For a plant crane, the lockout plan has three layers: the crane’s own maintenance precautions in 1910.179, the plant’s energy control program, and the electrical rules for the conductors that feed the crane.

The crane’s own precautions

Before adjustments and repairs start, 1910.179(l)(2)(i) requires the crane to be run to a location where it causes the least interference with other cranes and operations, all controllers placed at the off position, the main or emergency switch opened and locked open, warning or “out of order” signs placed on the crane and on the floor beneath or on the hook where visible from the floor, and rail stops or other suitable means where other cranes run on the same runway.

In an outage, park positions are worth planning: the crane needs to sit where the inspector can reach it and where it will not block another trade’s lift for a week.

Contractors, group lockout and the inspector’s lock

Turnarounds run on group lockout and outside personnel, and 1910.147 has specific requirements for both. Under (f)(2)(i), when outside servicing personnel work under the standard, the on-site employer and the outside employer inform each other of their lockout or tagout procedures, and (f)(2)(ii) requires the on-site employer to ensure its own employees understand and comply with the outside employer’s program.

Under (f)(3), group lockout uses a procedure that gives each worker protection equivalent to a personal lock, with primary responsibility vested in an authorized employee, a way to check each member’s exposure status, an authorized employee designated to coordinate when more than one crew is involved, and a personal device from each authorized employee on the group lockbox for as long as that person is working.

An outside crane inspector is one more set of hands under the group lock, and the planning question is simple: whose box does the inspector’s lock go on, and who briefs the inspector on the procedure. Paragraph (f)(4) adds that shift or personnel changes need specific procedures to keep lockout protection continuous, which matters for an inspection that spans more than one shift.

Electrical isolation

Conductor bars, collectors, panels and pendant stations expose electrical parts. Paragraph 1910.147(a)(1)(ii)(D) excludes from that standard exposure to electrical hazards from work on, near or with conductors or equipment in electric-utilization installations, which is covered by Subpart S, and 1910.333(b)(2) sets the lockout and tagging requirements for deenergized electrical parts. Note 2 to that paragraph accepts lockout and tagging procedures that comply with 1910.147(c) through (f) when they address the electrical hazards covered by the subpart and also incorporate 1910.333(b)(2)(iii)(D) and (b)(2)(iv)(B).

For the planner, the point is that the crane’s isolation points belong in the outage electrical isolation plan, not in a separate arrangement made at the crane on the day.

Putting power back for the function test

A complete periodic inspection includes operating the crane, so the plan needs the machine energized before the inspector leaves site. When lockout devices have to come off temporarily so equipment can be energized to test or position it, 1910.147(f)(1) sets the sequence: clear the equipment of tools and materials, remove employees from the area, remove the lockout or tagout devices as specified in (e)(3), energize and test, then deenergize and reapply energy control to continue the work.

Built into the outage schedule as a named event, a function test takes an hour. Left to chance, it waits until restart day, which is the worst time to find out that a limit switch does not trip.

Parts lead times: order for the findings you can predict

Many outage findings are not surprises. They are the next step of wear that last year’s report already described as a monitor item. A rope with a growing count of broken wires, a brake lining nearing its replacement point, a pitted contactor, a hook throat opening creeping toward its limit: each of those predicts a part, and the part has a lead time.

Plants that fold crane inspections into turnaround scope get a compounding benefit — the findings feed the next outage’s work list, parts get ordered on normal lead times instead of overnight freight, and the equipment never runs expired.

Likely outage findingWhere the warning shows up firstPlanning move
Hoist rope at or near removalMonthly rope inspections under 1910.179(m)(1): diameter reduction, broken outside wires, corrosion, end connection conditionConfirm the replacement rope’s construction, diameter and length against the manufacturer’s specification and have it on site
Brake linings, pawls or ratchets wornPeriodic item (j)(3)(v) and the brake adjustment historyStock linings and wear parts for the specific brake model
Contactors, limit switches or pushbutton stations deterioratedPeriodic item (j)(3)(x) and intermittent faults reported by operatorsOrder contact kits and switch parts, and check that obsolete controls still have parts available
Hook beyond its limitsThroat opening or twist trending toward the (j)(2)(iii) limits on monthly hook recordsReplace rather than repair; (l)(3)(iii)(a) says welding or reshaping is not generally recommended, and a repaired hook is tested to (k)(2) before further use
Hoist chain stretched or wornMonthly chain records under (j)(2)(iv), stretch beyond the manufacturer’s recommendationsOrder replacement chain to the manufacturer’s specification, along with any related parts the manufacturer calls for when chain is replaced
Wheels, rails or bumpers wornSkewing, flange wear and runway findings from earlier inspectionsPlan wheel sets and rail work as outage scope, with access booked
Pendant or festoon cable damageFrequent inspection notes and intermittent control faultsStock cable, strain relief and connectors for the specific station

Lead times vary by manufacturer, by part and by the age of the crane, and parts for older hoists and controls can take longer than the outage lasts. Ask the supplier when the scope is being built, not when the finding is written. Where a repair would change the crane from the manufacturer’s design, it stops being a parts question.

Under 1910.179(b)(3), a crane may be modified and rerated only if the modifications and the supporting structure are checked thoroughly for the new rated load by a qualified engineer or the equipment manufacturer, and that is work for them, not for the inspector.

Load-test logistics when a repair or alteration triggers a test

If repairs found early in the outage trigger a load test, schedule it after the repair crew finishes, with test weights already on site. That one sentence carries most of the planning, but in an outage a load test can slip for purely logistical reasons: the weights are not in the building, the slings are not rated for the test load, the floor under the staging area was never checked, or the test was booked for the same hour as the restart.

What triggers a test

Under 1910.179(j)(1)(i) and (k)(1)(i), new and altered cranes are inspected and tested before initial use, including hoisting and lowering, trolley travel, bridge travel, and limit switches, locking and safety devices. Under (k)(1)(ii), the trip setting of hoist limit switches is determined by tests with an empty hook traveling at increasing speeds up to the maximum speed.

Paragraph (k)(2) says test loads shall not be more than 125 percent of the rated load unless otherwise recommended by the manufacturer, and the test reports go on file where readily available to appointed personnel. Paragraph (b)(3) requires a crane that is modified and rerated to be tested in accordance with (k)(2), and (l)(3)(iii)(a) requires a hook repaired by welding or reshaping to be tested to the load requirements of (k)(2) before further use.

Whether a particular repair calls for a rated load test beyond those cases is answered by the manufacturer’s instructions, the ASME volume your program follows (B30.2 for overhead and gantry cranes, B30.17 for monorails and underhung cranes (it absorbed B30.11), B30.16 for overhead hoists) and often by the plant’s own policy or its insurer. The difference between the triggers and the folklore is laid out in overhead crane load testing.

Decide which cranes are likely to need a test while the scope is being built, because the logistics take longer to arrange than the test takes to run.

Test weights and how they reach the hook

A test load has to be known, not estimated: test weights of documented weight, or a calibrated load cell with a load whose weight is established. In an outage, the harder question is transport. Weights come through gates that are already congested, they need a forklift or another crane to place them, and they need a staging area near the test position that does not block another trade’s laydown.

Book the weights and the means to move them when the contractors are onboarded, and put the staging area on the outage site plan.

Rigging for the test

The slings, shackles and below-the-hook devices that connect the test load are loaded to the test load, not to the crane’s rated load. Under 1910.184(c)(4) and (c)(13), slings are not loaded beyond their rated capacity or the safe working load on their identification markings, so the test rigging has to be rated for the test load in the hitch actually used. That is a different set of slings from the ones the crane uses every day, and it needs to be identified and inspected before test day.

The floor, the structure and the path of the load

The test load sits on something before and after the lift: a floor slab, a grating platform, a trench cover, grade. Check what the staging area and the test position can carry before the weights arrive. Above the hook, the runway, the rails and the building steel carry the test load too. If anyone doubts the supporting structure, that is a question for the facility’s engineer before the test, not a discovery during it.

The test path also needs an exclusion zone: 1910.184(c)(9) requires employees to be kept clear of suspended loads and loads about to be lifted, and 1910.179(n)(3)(vi) requires the operator to avoid carrying loads over people. In a building full of outage contractors, the exclusion zone needs barricades and a person watching it.

Put the test late, with float

Run the test after every repair on the crane is complete, after the re-inspection, and before restart, with enough time left in the window for a retest if something adjusts, slips or fails to hold. A test that reveals a problem on the day of restart turns a planned restart into an unplanned extension.

When the test is done, the report goes on file under (k)(2), and if the crane was rerated, the new rated load is marked under (b)(5): on each side of the crane, and on each hoist or its load block where the crane has more than one hoisting unit, legible from the floor. How a proof load test is run is covered on our load testing and proof load services page.

Deficiency triage: fix before restart, or monitor

Every turnaround reaches the meeting where the restart date and the inspection findings meet. The classification of a finding does not change because the schedule is tight, and the plan should assume that some findings will come in after the parts order closed.

The federal rules for the triage are short. Under 1910.179(j)(2) and (j)(3), deficiencies are carefully examined and a determination made as to whether they constitute a safety hazard, and under (l)(3)(i), unsafe conditions disclosed by the inspections are corrected before operation of the crane is resumed. For mobile cranes in construction, 1926.1412(f)(4) through (f)(6) make the same split explicit: the qualified person determines whether a deficiency is a safety hazard or, though not yet a safety hazard, needs to be monitored.

A safety hazard takes the equipment out of service until it is corrected, except where the standard allows temporary alternative measures, and a monitored deficiency is checked in the monthly inspections.

CategoryTypical examplesBefore restart
Safety hazardA hook with cracks, more than 15 percent in excess of normal throat opening or more than 10 degrees of twist under (j)(2)(iii). Critical parts cracked, broken, bent or excessively worn under (l)(3)(iii)(c). A brake that does not hold. An upper limit switch that does not trip.Corrected, re-inspected and function tested, or the crane stays tagged out
MonitorMeasurable wear inside the limit but trending. Corrosion that has not reduced the section. A rope with broken wires below the removal criteria.Recorded with the measurement, checked at the frequent and monthly inspections, and carried into the next outage scope
Maintenance recommendationHousekeeping, lubrication, labels starting to fade, items that are cheaper to fix now than laterScheduled by maintenance, not a restart condition

When a hazard cannot be fixed before restart

Sometimes the part does not arrive, the repair finds more damage, or the fix needs a manufacturer or engineer who is not available inside the window. Then the crane does not restart with the plant.

It stays out of service with the precautions in (l)(2)(i) still in place while it waits for the repair — main or emergency switch locked open, “out of order” signs on the crane and on the floor beneath or on the hook — and the plant uses an alternative for the lifts that crane would have made: another crane, a rented mobile crane with its own inspection file, or a revised lift plan.

The plan should name that fallback for the cranes most likely to need it, because inventing it on restart day is how a hazard gets reclassified as a monitor item. What follows a failed item, from triage to sign-off, is covered in what happens after a failed crane inspection.

Make the findings usable

A triage meeting works only if each finding states the condition, the measurement, the criterion and the paragraph it is measured against, so the outage team can see why it is a hazard or a monitor item without taking anyone’s word for it. How to read a report that way, and what a defensible finding contains, is in reading a crane inspection report. Hook findings in particular depend on reference measurements, which crane hook inspection limits explains.

The restart sequence: returning cranes to service

Restart day compresses everything. Locks come off in bulk, every unit wants its crane back at once, and the crane that was opened up, repaired and tested is expected to run the next shift. A written sequence per crane keeps the steps from collapsing into one another:

  1. Repairs complete and documented. Every safety-hazard finding is closed with a record of what was done and by whom, under 1910.179(l)(3)(i).
  2. Repaired items re-inspected. For mobile cranes in construction, 1926.1412(b)(1) requires a qualified person to inspect equipment after a repair or adjustment that relates to safe operation, prior to initial use, including functional testing of the repaired parts and other components that may be affected. Section 1910.179 has no paragraph worded that way for plant cranes, but (l)(3)(i) requires unsafe conditions to be corrected before operation resumes, and a re-inspection of the repaired items is how the plant shows that they were.
  3. Guards back, safety devices reactivated, maintenance equipment removed, under (l)(2)(ii), including scaffolds and staging in the crane’s path and any rail stops installed for the outage.
  4. Release from lockout under 1910.147(e). The work area is inspected so nonessential items are removed and components are operationally intact, employees are safely positioned or removed, affected employees are notified that the devices have been removed, and each device is removed by the employee who applied it, or under the employer’s documented exception procedure.
  5. Function test with an empty hook. Hoisting and lowering, trolley travel, bridge travel, limit switches, locking and safety devices, the list in (k)(1)(i), plus the controls and stop functions covered in pendant and radio control inspection. On a new or altered crane, the hoist limit switch trip setting is set by the empty-hook tests in (k)(1)(ii).
  6. Idle rope inspection where it applies. Paragraph (m)(2) requires rope that has been idle for a month or more due to shutdown or storage of the crane to be given a thorough inspection before use, by an appointed person whose approval is required for further use, with a certification record showing the date, the inspector’s signature and the rope identifier. A long outage triggers it on its own.
  7. Idle crane inspection where it applies. Under (j)(4)(i), a crane idle for 1 month or more but less than 6 months gets the (j)(2) items and the (m)(2) rope inspection before it is placed in service. Under (j)(4)(ii), a crane idle more than 6 months gets the complete (j)(2) and (j)(3) inspection plus (m)(2). Mobile equipment in construction idle for 3 months or more is inspected by a qualified person to the monthly requirements before initial use under 1926.1412(h).
  8. Load test where triggered, with the report on file under (k)(2) and the rated load marking updated under (b)(5) if the crane was rerated.
  9. Operators back on the crane. At the beginning of each operator’s shift, the upper limit switch of each hoist is tried out under no load under (n)(4)(i), and the brakes are tested when a load approaching the rated load is handled under (n)(3)(vii). The first heavy lift after an outage is a good time to remember both.
  10. Records closed out before the outage team disbands.

The deep inspection early in the window and the restart checks at the end are two different inspections with two different purposes, and a long outage needs both. The fuller treatment of cranes coming back from idle time is in return-to-service inspection, and rope removal criteria are in the crane wire rope inspection guide.

Records that close this window and open the next

An outage generates a burst of crane records in a few weeks, and most of them are needed again in the next outage. Before the team disbands, the crane file for each machine should hold:

What each kind of record should show and how long to keep it is covered in crane inspection documentation.

Refineries, power plants and production lines: the same planning problem

The vocabulary changes by industry, the problem does not. In refineries and petrochemical plants it is a turnaround: process cranes and maintenance bay cranes come down with the unit, crawlers arrive for exchanger pulls and module work, and the cranes inside classified areas may only be reachable while the unit is down. The standards stack for that environment is on the oil, gas and petrochemical crane inspections page.

In power generation it is an outage: a turbine hall crane can run hard through a maintenance outage, which is an argument for inspecting it at the front of the window, and the power and energy crane inspections page covers that environment. In manufacturing it is a shutdown, often a holiday or retooling week, with bay cranes over production lines that never stop otherwise, and the approach for that environment is on the manufacturing overhead crane inspections page.

In all three, the ASME B30 volumes sit under the federal text as the consensus criteria: B30.2 for overhead and gantry cranes, B30.17 for monorails and underhung cranes (it absorbed B30.11), B30.16 for overhead hoists, B30.9 for slings, B30.20 for below-the-hook devices, and B30.5 for the mobile cranes that come in for the outage. The edition your program has adopted, together with the manufacturer’s manual, is where the detailed criteria are read.

The planning work is the same everywhere: a register, a scope, a slot in the schedule of record, an early inspection, a parts list, a lockout plan, a load-test plan where one is likely, a triage rule and a restart sequence.

Common questions

When should crane inspections be scheduled during a plant shutdown?

As early in the window as the crane can be locked out. Under 1910.179(l)(3)(i), unsafe conditions found by inspection are corrected before the crane resumes operation, so the time between the inspection and the planned restart is the only time available for repairs. Inspect the cranes that need deep work, and the cranes the outage will use heavily, in the first days, and leave the re-inspection, function tests and any load test for the end.

Does a plant shutdown count as idle time for crane inspection purposes?

It can. Under 1910.179(j)(4), a crane idle for 1 month or more but less than 6 months gets the frequent inspection items in (j)(2) and the rope inspection in (m)(2) before it is placed in service, and a crane idle for more than 6 months gets the complete inspection. Paragraph (m)(2) applies on its own to rope that has been idle for a month or more due to shutdown or storage of the crane. For mobile cranes in construction, 1926.1412(h) applies to equipment idle for 3 months or more.

Can the periodic crane inspection wait for the next turnaround?

Only if the turnaround falls inside the crane’s periodic interval. Under 1910.179(j)(1)(ii)(b), periodic inspections run at 1 to 12 month intervals, set by the crane’s activity, severity of service and environment under (j)(3). If the next window comes later than that, the periodic inspection is done on the running plant, and the outage adds the work that needs the crane locked out.

Do we need a load test after repairs made during a turnaround?

It depends on the repair. Under 1910.179, new and altered cranes are inspected and tested before initial use under (j)(1)(i) and (k)(1)(i), a modified and rerated crane is tested under (k)(2) per (b)(3), and a hook repaired by welding or reshaping is tested to (k)(2) before further use under (l)(3)(iii)(a). Test loads are not more than 125 percent of the rated load unless the manufacturer recommends otherwise. Beyond those cases, the manufacturer’s instructions, the ASME volume your program follows and your own policy decide.

Plan the logistics early either way: weights, rigging rated for the test load, staging, and floor capacity.

Can a crane restart with open findings after a turnaround?

Monitor items, yes. Safety hazards, no. Under 1910.179(l)(3)(i), unsafe conditions are corrected before operation resumes. A deficiency that is not yet a safety hazard can be recorded with its measurement and checked at the frequent inspections until it is repaired, which for mobile cranes in construction is the monitoring route in 1926.1412(f)(6). A crane with an open safety hazard stays tagged out, and the plant uses another means for its lifts.

Who inspects the slings contractors bring in for a turnaround?

Under 1910.184(d), each sling and its fastenings and attachments are inspected each day before use by a competent person designated by the employer, and damaged or defective slings are removed from service immediately. Slings without affixed and legible identification markings are not used under (c)(14). A host plant gate check on contractor rigging is a common site practice on top of that, not a federal requirement.

How does lockout work for an outside crane inspector during a turnaround?

Inspecting is part of the definition of servicing and/or maintenance in 1910.147, so an outside inspector working on a locked-out crane is outside servicing personnel under (f)(2). Paragraph (f)(2)(i) requires the plant and the inspector’s employer to inform each other of their lockout or tagout procedures, and (f)(2)(ii) requires the plant to ensure its own employees understand and comply with the restrictions and prohibitions of the outside employer’s program.

In a turnaround run on group lockout, the practical result is usually that the inspector’s personal lock goes on the group lockbox under (f)(3) for the cranes being inspected, under procedures both employers have reviewed before the window opens.

Put the inspector on the outage schedule before the gates open

The cranes that come out of a turnaround in better shape than they went in are the ones whose inspection had a work order, a slot and a parts list before the first lock went on.

Tell us when your next outage window opens and send us the equipment register, and we will scope the overhead crane inspection around your lockout windows and repair crews, inspect each crane against 1910.179 and the manufacturer’s criteria, and deliver the findings in a written report within 24 to 72 hours, early enough that the repairs still fit inside the window.

Reviewed by Patrick Salazar, NCCCO-Certified Crane Inspector — every article on this site is checked against current OSHA and ASME B30 requirements before it publishes.

← All Posts

Ready to Schedule Your Inspection?

Tell us your equipment types, locations, and inspection window. Our inspectors, led by an NCCCO-certified crane inspector (MCI · TCI), mobilize nationwide in 24 to 72 hours, and every engagement closes with a photo-documented, standards-cited report.