OSHA 1926.1412 Mobile Crane Regulations

OSHA 1926.1412 is the inspection rule for cranes on construction sites. It sits inside Subpart CC and spells out every inspection a crane needs — after assembly, each shift, monthly, annually, and after anything that could have hurt the machine. This guide walks the rule subsection by subsection, in plain terms, so you know exactly what each one asks for and who has to do it.

153+
Cities Served
50
States Covered
24–72h
Scheduling
100%
NCCCO Certified
✓ NCCCO Inspector Certified ✓ OSHA & ASME B30 Compliant ✓ Photo-Documented Reports ✓ Independent Third-Party ✓ EM 385-1-1 · USACE · NAVFAC

We are 3P Safety Inspections, a third-party crane inspection company working all 50 states. Our inspectors hold NCCCO cards. We inspect to OSHA and the ASME B30 codes, and we do not sell or rent cranes — so our reports just give you the facts.

Independent Third-PartyWe do not sell or rent cranes. Our report has no sales angle — just the facts.
NCCCO-Certified InspectorsEvery inspection is signed by a credentialed, qualified-person inspector.
24-72 Hour SchedulingQuotes in about a business day. We reach most sites in 24 to 72 hours.
Photo-Documented ReportsA clear PDF with each finding tied to a photo and the exact OSHA or ASME rule.
Inspecting cranes since 2005Independent — we do not sell or rent cranesNCCCO-certified inspectorsAll 50 states · 24–72 hr schedulingPhoto-documented reports
Free Printable Checklists (PDF)

Where 1926.1412 Fits

The rule is one piece of a larger framework. Know the neighbors:

1926.1412(a) and (b) — Modified or Repaired Equipment

If a crane is modified (a), or a load-bearing part is repaired or adjusted (b), a qualified person inspects the affected parts before the crane goes back to work. The point is simple: prove the change is safe before the next lift. We document the check so it holds up later.

1926.1412(c) — Post-Assembly

After a crane is assembled on site, a qualified person inspects it to confirm it was put together right and matches the manufacturer’s setup. This catches the assembly error before it becomes an incident. Here is how we run a post-assembly crane inspection.

1926.1412(d) — Each Shift

A competent person makes a visual check at the start of (or during) each shift the crane is used. It is quick, but it is required every shift. It covers:

1926.1412(e) — Monthly

Each month a competent person runs the same shift-level check, documents it, and signs it. The record names the equipment and the parts checked, and it is kept on file for at least three months under 1926.1412(e)(3). This monthly document is the layer OSHA most often finds missing.

1926.1412(f) — Annual / Full

At least every 12 months a qualified person inspects the whole machine in depth. The annual record is kept at least 12 months under 1926.1412(f)(7). It covers:

1926.1412(g) and (h) — Severe Service and Idle Equipment

Two more triggers round out the rule:

What Happens to a Deficiency

When a check finds a problem, 1926.1412 splits it two ways. A deficiency that is a safety hazard takes the crane out of service until it is fixed. A deficiency that is not an immediate hazard gets evaluated by a qualified person, who decides whether the crane can keep working. Our reports make that call clear — each finding is ranked so you know what stops a lift and what can wait.

Which Cranes 1926.1412 Covers

The rule applies across the mobile-crane family on construction sites:

Crane Inspection Frequency at a Glance

InspectionHow OftenWho Performs ItWhat It CoversRecord Kept?
Pre-shift / DailyBefore each shift or useCompetent person (often the operator)Controls, brakes, wire rope, hooks, leaks, tires or tracks, safety devicesGood practice
MonthlyEvery 30 daysCompetent personWire rope along its length, hooks and latches, hoist brakesYes — signed and dated
FrequentDaily to monthly, by service classCompetent personRunning gear and high-wear items per ASME B30Per your program
Annual / PeriodicEvery 12 monthsQualified personThe full machine: structure, welds, sheaves, drums, hydraulics, controlsYes — full written report
After an eventAfter a repair, modification, storm, or idle periodQualified personThe affected systems, before the crane returns to serviceYes

The Standards Behind These Checks

Every report names the rule behind each find:

What You Get in Your Report

Here is what lands in your inbox:

Why Owners Pick 3P Safety Inspections

We do not sell or rent cranes, so the report has no angle. We show up when we say and write reports a foreman can read. The quote is the price.

Frequently Asked Questions

What does OSHA 1926.1412 require?

It requires inspections of construction cranes after modification (a), after repair (b), after assembly (c), each shift (d), monthly (e), annually (f), under severe service (g), and after an idle period (h). Shift and monthly checks go to a competent person. The annual goes to a qualified person.

What is checked on the 1926.1412(d) shift inspection?

Control mechanisms, pressurized lines for leaks, hooks and latches, wire rope for obvious damage, tires or tracks and the supporting ground, and the safety devices and operator aids — a quick visual and functional check before each shift.

How long must 1926.1412 records be kept?

The monthly documented inspection is kept at least three months (1926.1412(e)(3)) and the annual inspection at least twelve months (1926.1412(f)(7)).

Who can perform the annual inspection under 1926.1412(f)?

A qualified person — someone with the recognized degree, certificate, or extensive experience to evaluate the equipment under 1926.32(m). Our inspectors are NCCCO-certified and meet that bar.

What does 1926.1412 say about idle cranes?

Under (h), a crane idle three to six months gets a monthly-level inspection before reuse. One idle longer than six months gets an annual-level inspection. Both are documented before the crane lifts.

What happens when an inspection finds a deficiency?

A deficiency that is a safety hazard takes the crane out of service until repaired. One that is not an immediate hazard is evaluated by a qualified person, who decides whether the crane can keep working. Our reports rank each finding.

Does 1926.1412 cover wire rope?

The shift and monthly checks look at wire rope for obvious damage, but wire rope has its own dedicated rule, 1926.1413, with detailed removal criteria. The annual inspection applies those criteria.

Do you inspect mobile cranes to 1926.1412 nationwide?

Yes. We inspect rough-terrain, all-terrain, truck-mounted, crawler, and carry-deck cranes in all 50 states, with NCCCO-certified inspectors and 24-to-72-hour scheduling.

Authoritative References

OSHA 1926.1412 — Construction Crane InspectionThe official standard, straight from the source.Visit source about OSHA 1926.1412 — Construction Crane Inspection
OSHA 1910.179 — Overhead & Gantry CranesThe official standard, straight from the source.Visit source about OSHA 1910.179 — Overhead & Gantry Cranes
ASME B30 — Safety Standard for Cranes & RiggingThe official standard, straight from the source.Visit source about ASME B30 — Safety Standard for Cranes & Rigging
NCCCO — Crane Operator & Inspector CertificationThe official standard, straight from the source.Visit source about NCCCO — Crane Operator & Inspector Certification

Ready to Schedule Your Inspection?

Tell us your equipment types, locations, and inspection window. NCCCO-certified inspectors mobilize nationwide in 24 to 72 hours, and every engagement closes with a photo-documented, standards-cited report.